Portfolio

Durbanville - Commercial 50Kw SolarHybrid

Phase 2 of a Project at a Medical clinic in Durbanville

The Project was a new build and we supported the main contractor

We Installed 50KWp of Solar with 610W Longi Solar Panels

The Client provided a 110KW Freedomwon Low voltage Battery

We therefor Installed 2 X 20KW Low Voltage Deye Inverters

The Installation took 2 weeks as we had to wait a few days for site readyness

The system is monitored on the Deye Cloud App

 

 

Solutions
Deye High Voltage Batteries Sunwoda Revov Lithium Jinko Solar PV Green card JINKO